Deaerator Replacement Project Colgate University, NY Services:
- Detailed design development
- Construction support services
Schedule: Ongoing
Budget: $50,000 (design fee)
Tasks:
- Design Condensate Receiver and Deaerator with capacity to handle 125,000 lbs/hr
- Design new condensate receiver Pumps
- Support Bid Process
- Construction Phase Support Services
Project Highlights:
- O’Brien & Gere was retained by Colgate University to design and provide bidding documents to replace the condensate receiver and deaerator and related appurtenances with an increased capacity of 125,000 lb/hr units.
- Major Tasks
- Demolition Plans
- Flow Diagrams
- Mechanical and Electrical Design Drawings
- Catwalk Framing Details
- Structural Steel Support Systems
|