Utilities Assessment



Utilities Assessment
University of Rochester, NY


Services:     

  • Chilled water generation and distribution
  • Electric power service and distribution
  • Short circuit coordination study

Schedule: 13 months

Budget:
$72,000


Tasks:  
  • Conduct utility surveys
  • Compile data
  • Develop new or update existing schematic diagrams and plans
  • Provide documentation of findings from each assessment

Project Highlights:  
  • Developed one-line schematic diagrams of the steam plant (including steam, feedwater, condensate and make-up water).
  • Documented the condition of steam generation equipment.
  • Identified system components whose failure could cause major loss of steam system services.
  • Identified areas where electrical capacity might be inadequate or potential reliability problems might exist.
  • Updated a 1970 short circuit and coordination study to identify current levels of short circuit current.
  • Developed fuse ratings and relay setting that accurately reflect current characteristics.