Regional Wastewater Treatment Plant Feasibility Study Confidential Client, North Carolina Services: Feasibility Study
Schedule: 4 Months
Budget: $83,000
Tasks:
- Feasibility Study
- Basis-of-Design
- Regulatory Assessment
- Life-cycle Cost Analysis
- Conceptual Design
- Cost and Schedule Estimate
Project Highlights:
- Performed a feasibility study to evaluate the economic and technical feasibility of constructing a new wastewater treatment plant (WWTP)
- Projected organic and nutrient loading rates (and loading rate variability) for start-up and out-year conditions for existing and prospective pharmaceutical process waste streams
- Assessed commercially available and proprietary technologies to pretreat industrial process wastewater and performed life-cycle optimization analysis for each
- Developed conceptual design and regulatory framework for the new regional WWTP
- Developed conceptual estimates for the design, construction, and operational costs for the new regional WWTP
- Developed permitting, design, construction, and financing strategies to facilitate WWTP start-up
- Conducted rate structure analysis for the two existing pharmaceutical industries and anticipated new pharmaceutical users
- Prepared ownership and financing plan based upon public financing and ownership, and prepared alternative plan based upon private financing and ownership