Emergency Generator Power Program Pharmaceutical Client, Swiftwater, Pennsylvania Services:
- Engineering
- Electrical Safety Audit
Schedule: 24 Months
Budget: $160,000
Tasks:
- Electrical support
- Emergency and Standby Power generation plan
- Electrical distribution one-lines
- Needs Analysis
- Site-wise emergency generation power plan
Project Highlights:
- Reviewed overall facility site plan for current and future building arrangements
- Reduced on-site air emissions
- Determined life/safety code requirements per specific building design and use
- Conducted physical site surveys of buildings to verify electronic data gathered,electrical system evaluation, and load determinations
- Designed specification of 600V equipment including automatic transfer switches, panelboards, MCC units, low emission generators, UPS units, and emergency lighting products
- Performed submittal reviews and complied cost estimate for complete project, and time-line for construction
- Completed design of building integration with site stream and chilled water system
- Completed electrical site plan design, including location and placement of motor starters, VFD's conduits and heat trance sub-panels
- Developed equipment and material specifications
- Performed testing on two boilers measuring particulate matter emissions
- Performed testing in accordance with 40CFR60 Subpart Dc and the Pennsylvania DEP source test manual