Confidential Client, Pennsylvania 


Services:     

  • Plant Upgrade 
  • Regulatory Compliance Negotiations

Schedule: 22 Months

Budget: $16.6 Million


Tasks:  
  • Coordination of Design Activities
  • Scheduling and Estimating
  • Pre-Construction
  • Constructability Reviews
  • Purchasing
  • Project/Construction Management
  • Quality Control
  • Safety and Start-up
  • Validation
  • Commissioning  

Project Highlights:    
  • Pilot testing and basis of design development for the installation of a new MBBR system identified problems of additional operational complexity, potential odor considerations, and elevated implementation costs
  • Removed biofilters from service by expanding the conventional activated sludge system at the WWTP
  • Relocated the existing 69 kV power line that currently transects the WWP site and installed a new double-ended electrical substation Demolished primary clarifier as necessary to accommodate the footprint of the new activated sludge reactors
  • Constructed three new above ground activated sludge tanks with secondary containment
  • Installed new jet aeration system in each new activated sludge tank complete with in-basin aeration headerlnozzles, aeration blowers, and mixing pumps