Potable Water System Upgrade Confidential Client, Pennsylvania Services: Plant Upgrade and Expansion
Schedule: 8 Months
Budget: $17,000
Tasks:
- Demolition of existing water tank, standpipe, roadway, and fencing
- Removal of fuel oil tanks and related equipment
- Relocation of electrical utilities, well and potable water lines, and fire protection system
- Installation of communication connections and data circuits
- Establishment of new underground utilities
- Installation of temporary fire main cross connections
- Soil management and disposal
Project Highlights:
- Increased the utilization of existing aquifer capacity
- Improved delivery pressure throughout the distribution system
- Provided water in quantities and pressures necessary to support projected growth
- Reduced site vulnerability issues caused by temporary loss of water supply from the Water Authority
- Installed over 21,000 If of pipeline, a 6 MG ground level water storage tank, a 2 MG elevated water storage tank, and a new pumping station
- Connected new facility to existing water supply and distribution systems
- Installed new chlorination system
- Provided connection to plant water corrosion control system
- Upgraded computerized control network