Raw water screening
Two travelling screens, “fish- friendly” design
7’-8” wide each
Raw water pumping
Two 150-HP pumps (7.5 MGD each)
Two 250-HP pumps (10 MGD each)
Rapid mixing
One 2-stage basin
Detention time – 34 seconds
Flocculation
Three 4-stage basins
Detention time – 30 minutes
Clarification
Three basins equipped with stainless steel inclined plates
Chain and flight sludge collection
|
Filtration
Ten gravity filters (Six existing/rebuilt, four new)
595 square feet each
12” sand and 31” GAC filter media
Waste handling
Five freeze-dry beds, 4.9 acres total plan area
Two backwash waste lagoons (existing)
Chemical treatment systems
Chlorine dioxide (oxidant, preliminary disinfection)
Sulfuric acid (raw water pH adjustment)
Aluminum sulfate (primary coagulant)
Polymers (coagulant aid and filter aid)
Sodium hydroxide (filtered water pH adjustment, corrosion control)
Chlorine (primary and residual disinfection)
|