Pumped Storage Reservoir Project

O’Brien & Gere provided basis of design, preliminary design, final design, permitting assistance, bid assistance, resident inspection, and startup assistance services for the development of a new 1.0 billion gallon pumped storage reservoir for the Brick Township Municipal Utilities Authority, NJ. The final construction cost, at $19.4M, was below the final approved budget amount for the reservoir project, and the project benefited from the Authority’s success in having approximately 800,000 cubic yards of on-site material removed from the site at virtually no cost to the Authority. Preliminary estimates had factored in a cost of $2.4M to remove this quantity of material.
location:
Brick, NJ
highlights:
Provided a verifiable safe yield to meet long-term demand requirements, storage system for raw water, and protection against loss of sources.