Antibiotic Manufacturing Process Segregation Project Pharmaceutical Manufacturer, PA Services:
- Detailed Design
- Procurement
- Start-up
- Validation
- Construction Management
Schedule:20 Months
Budget: $4,300,000
Tasks:
- Process segregation
- Relocation and demolition of existing facilities
- Design of glove boxes
- Installation of drum washer
- Design of an air lock segregation room
- Design of pressure transmitter and isolation valves
- Decontamination of non-antibiotic process areas
- Segregation of HVAC systems
- Design of HEPA filters and exhaust monitoring
- Area pressurization monitoring