R&D and Pilot Plant Manufacturing Facility


R&D and Pilot Plant Manufacturing Facility
PAR Pharmaceuticals, NJ


Services: Construction Management     

Schedule:
15 Months

Budget:  $18,000,000
 Tasks: 

  • Engineering Design
  • Estimating
  • Procurement
  • Project Management
  • Start-up
  • Commissioning
  • Validation

Tasks/Project Highlights:
  • Demolished existing interior space 
  • Modified existing roof structure 
  • Performed constructability review of design and made change recommendations 
  • Obtained state and local building permits 
  • Installed new process and utility underground systems, including waste neutralization system and pit 
  • Relocated existing services 
  • Constructed new office support space 
  • Constructed new R&D, QC, and QA Laboratories, including lab services and gases, casework, hoods, mass balance suite, and scientist work area 
  • Constructed new class 10,000 pilot plant manufacturing suites, including HVAC systems, process utilities, WFI, and USP water systems including generation skids 
  • Constructed new class 1000 manufacturing suite, including all services 
  • Installed new validated HVAC and utility systems Installed new dust collection system 
  • Performed start-up and commissioning of systems 
  • Coordinated final inspections, and obtained Certificate of Occupancy
 