Hydropillar Replacement at Pharmaceutical Manufacturing Plant


Hydropillar Replacement at Pharmaceutical Manufacturing Plant

Confidential Client, Pennsylvania 

Services:
Design and Construction Management

Schedule: 24 Months

Budget:
$17 Million


Tasks:

  • Coordination of Design Activities 
  • Scheduling
  • Pre-Construction Estimating
  • Constructability Reviews                                 
  • Purchasing
  • Project Management
  • Quality Control
  • Safety
  • Start-up Commissioning
  • Validation  

 Project Highlights:
  • Hydropillar with 2MM gallons of elevated storage
  • New pump house with redundant pumping systems
  • New underground distribution piping systems tied into existing site systems
  • Relocation of existing overhead piping and electrical systems to clear the footprint for the new Hydropillar
  • Included clean, flush, and startup of pumping system


 