Wastewater Treatment Plant Design-Build

 

Wastewater Treatment Plant Design-Build
Carrier Corporation, Collierville, TN 

Services:
  • Design
  • Construction
Schedule: 8 Months

Budget: $1,500,000


Tasks:
  • Process segregation and control strategy
  • Building design
  • Utility and infrastructure system design
  • Site work
  • Exterior tank farm design
  • Construction scheduling
  • System integration and commissioning

Project Highlights:

  • Fast-track design-build of a wastewater treatment facility for metals removal
  • Provided removal of metals from high pH wastewater associated with a painting process line
  • Coordinated compressed design schedule and budgets for a multi-discipline design team
  • Developed P&IDs and process control strategies
  • Designed influent flow EQ tankage, treatment reactors for pH control, and metals precipitation, a lamella clarifier, sand filtration system and final pH adjustment systems
  • Designed an insulated metal process building and associated HVAC, fire protection, and communication systems
  • Designed and constructed new PLC-based control system and touch screen panel to allow automatic operation and monitoring
  • Designed exterior tank farm for EQ tanks, sludge storage tank, and water reuse tank
  • Coordinated construction scheduling closely with decommissioning of the former facility in order to reuse selected equipment from the former facility in the new facility
  • Seamless transition from the existing wastewater treatment system to the new system ahead of schedule.