Plant Decommissioning and Demolition Chemical Manufacturer, New Jersey Services:
- General Information Notice
- Preliminary Assessment
- Site Investigation Activities
- Remedial Investigation (RI) Work Plan
- Remedial Investigation
- Remedial Alternative Assessment
Schedule: 8 Years
Budget: $1.2 Million
Tasks:
- Facility Closure, Decommissioning, and Dismantling
- Chemical Delineation
- Bid Specifications and Contract Document Development
- Construction Oversight and Administration Services
- RCRA-Permitted Hazardous Waste Storage Unit Closure
- NJDEP and USEPA Region II Coordination
- RCRA Closure Negotiations
- NJDEP DGW Permit Removal Negotiations
- Remediation Strategy Development
- Source LNAPL Removal and Exposure Issues
- Site-Wide Assessment and Remedial Action
Project Highlights:
- Decommissioned and dismantled facility as part of closure process
- Delineated facility for contaminants of concern
- Collected more than 300 soil samples from various depths to evaluate soil conditions.
- Negotiated variance from area of concern delineation to a site wide zone concept
- Developed remediation strategy to include deed restriction limiting future use scenarios, and ground water classification exemption
Return to Project listing
|