Wyeth Holdings Corporation, Bound Brook Remedial Program Former Chemical Manufacturing Facility, Bound Brook, New Jersey
Services:
- Environmental Studies
- Chemical Sampling and Analysis
- Preliminary Assessment
- Mitigation/Ecosystem Restoration
- Technical Reports
Schedule: 1982 - Present
Budget: $100 Million
Tasks:
- Section 404 Permit Evaluations
- Biological Assessments of Fish and Wildlife
- Environmental Restoration Planning and Design, Cost Effectiveness and Incremental Cost Analyses
- Public Presentations
- Bioassays Testing
- TCLP Testing
- Bulk Sediment Testing
- Familiarity with Drinking Water Requirements
- Site Specific Health and Safety Plans
- Chemical Data Acquisition Plans
- Review of Existing Project Material and Literature
- Site Visits
- Coordination with Federal, state, and local agencies
- Review of historic records and maps and aerial photographs and databases relative to hazardous waste sites and hazardous spills
- Preliminary Surveys
- Agency Coordination
- Wetland Design Assistance
- Endangered Species Surveys
- Population Studies
- Habitat Evaluation
- Site Mapping (Utilizing GIS)
Project Highlights:
- Blending of contents from two lagoons into usable mixture for incineration off-site as fuel
- Design of pumping system to pump 3 MG of viscous, organic tar sludge into trucks for off-site disposal air emission control system to minimize volatile emissions
- Design of on-site wastewater treatment system for oil-water separation, neutralization, and carbon treatment
- Solidification-stabilization of remaining lagoon sludge
- Encapsulation of lagoons following removal of aqueous layer
- Design review, modifications, construction, and construction oversight of a one million yd3 RCRA on-site hazardous waste facility
- Built in four cells, serving as a disposal site for dewatered, excavated, and treated lagoon materials
- Utilization of stabilized material for internal berm of landfill cell, resulting in a $500,000 cost savings