Schedule: 2 years
Budget: $13 Million
Tasks:
- Screening evaluations
- Mitigation system design
- Installation and commissioning
- Air dispersion modeling
- Ambient air monitoring
- Data management
- Community relations
- Value engineering
Project Highlights:
- Largest VI site in the United States
- 350 acre study area
- Provided design, construction and commissioning services associated with the installation of nearly 500 sub-slab depressurization systems
- Advanced the state of the science with respect to sampling, analysis, data interpretation and risk assessment
- Two year project involving more than 65 engineers and scientists